Level platform handed to main contractor
All Case Studies
Civil & Earthworks

Henderson Site Preparation

Henderson, Auckland10 weeks · 2026Tier-1 main contractor (early works package)
4,800 m²
Site area
6,200 m³
Cut/fill
10 weeks
Duration
On programme
Handover
Before & After

From hazardous to handover-ready.

Before
Brownfield site prior to earthworks
Before — cleared brownfield site
After
Level platform handed to main contractor
After — level platform surveyed for handover
Toggle view
Brownfield site prior to earthworks

Before — cleared brownfield site

Case Overview

How Sline delivered this project.

An early-works package for a Tier-1 main contractor covering hazard clearance, bulk earthworks and certified erosion controls, delivering a level, safe, survey-set platform for structural works to begin.

Our Approach

  • GPR service scan prior to any ground disturbance
  • Silt fences, stabilised entry and dewatering managed daily
  • Machine-guidance GNSS for level-to-datum accuracy
  • Weekly progress survey shared with the principal
Site Gallery

Multiple points of view.

Documented views from across the programme — safety controls, plant movements and compliance milestones.

Bulk excavation in progress
Bulk cut-to-fill with GNSS machine guidance
Silt fence and stabilised entry
Certified ESC — silt fence & stabilised entry
Surveyor checking levels
Setout survey handover to main contractor