Remediated site ready for redevelopment
All Case Studies
Contaminated Soil

Penrose Industrial Soil Lift

Penrose, Auckland5 weeks · 2024Industrial landowner (former workshop site)
1,100 t
Volume
up to 2.4 m
Depth
5 weeks
Duration
Passed
Validation
Before & After

From hazardous to handover-ready.

Before
Contaminated ground prior to remediation
Before — impacted ground identified in DSI
After
Remediated site ready for redevelopment
After — validated clean site ready for consent
Toggle view
Contaminated ground prior to remediation

Before — impacted ground identified in DSI

Case Overview

How Sline delivered this project.

A decommissioned mechanical workshop required hydrocarbon remediation before redevelopment consent could be granted. Sline delivered the excavation, tracking and validation programme under the National Environmental Standard for Contaminated Soils (NES-CS).

Our Approach

  • PID field screening on every truckload prior to load-out
  • Sealed truck movements with wheel-wash and manifest tracking
  • Bunded stockpile area with runoff capture
  • Post-excavation validation sampling on a 10m grid
Site Gallery

Multiple points of view.

Documented views from across the programme — safety controls, plant movements and compliance milestones.

Excavator lifting impacted soil
Staged excavation with field screening
Bunded stockpile area
Bunded stockpile with runoff capture
Validation sampling
Independent validation sampling grid