New roof deck installed
All Case Studies
Class B Asbestos

Manukau Commercial Reroof

Manukau, Auckland2 weeks · 2025National logistics operator
1,800 m²
Roof area
Night works
Shift
0 hours
Downtime
Class B
Licence
Before & After

From hazardous to handover-ready.

Before
Asbestos-cement roofing prior to removal
Before — non-friable AC roof sheets in place
After
New roof deck installed
After — deck cleared for reroof contractor
Toggle view
Asbestos-cement roofing prior to removal

Before — non-friable AC roof sheets in place

Case Overview

How Sline delivered this project.

The client operates a 24/6 logistics facility that could not accept daytime disruption. Sline programmed a staged night-works removal of non-friable asbestos-cement roofing across six weekend windows.

Our Approach

  • Isolation of live services and after-hours coordination
  • Full edge protection installed ahead of each shift
  • Double-wrapped panels manifested to licensed landfill
  • Toolbox talks and Class B supervisor sign-on nightly
Site Gallery

Multiple points of view.

Documented views from across the programme — safety controls, plant movements and compliance milestones.

MEWP access at night
MEWP access under floodlighting
Wrapped panels prepared for disposal
Double-wrapped panels awaiting manifest
Edge protection and safety netting
Full edge protection and safety netting